Appeal No. VA98/3/039
AN BINSE LUACHÁLA
VALUATION TRIBUNAL
AN tACHT LUACHÁLA, 1988
VALUATION ACT, 1988
Kilsaran Concrete APPELLANT
and
Commissioner of Valuation RESPONDENT
RE: Sand Pit at Map Reference 1B, Townland: Ballynamona, E.D. Galtrim,
R.D. Trim. Co. Meath
Quantum - Methodology for valuing a quarry
B E F O R E
Con Guiney - Barrister at Law Deputy Chairman
Finian Brannigan - Solicitor Member
Barry Smyth - FRICS.FSCS Member
JUDGMENT OF THE VALUATION TRIBUNAL
ISSUED ON THE 26TH DAY OF JULY, 1999
By Notice of Appeal dated the 4th day of August 1998 the
appellant appealed against the determination of the Commissioner of
Valuation in fixing a rateable valuation of £522 on the above
described hereditament.
The Grounds of Appeal as set out in the said Notice of Appeal are that;
"the valuation is excessive, inequitable and bad in law when rental
levels and other factors are taken into account".
The appeal proceeded by way of an oral hearing, which
took place on the 1st day of March 1999 at the offices of the Valuation
Tribunal, Dublin. The appellant was represented by Mr. Brian Bagnall
of Bagnall & Associates and Mr. John Barnett of John Barnett &
Associates Ltd., Chartered Mineral Surveyors. The Respondent was represented
by Mr. John Colfer A.R.I.C.S., a Valuer in the Valuation Office.
Having taken the oath both Mr. Barnett and Mr. Colfer
each adopted as his evidence in chief his written submission, which
had previously been exchanged with the other and submitted to the Valuation
Tribunal.
Material Facts agreed or found by the Tribunal
1. Valuation History
Following inspection of the property in October 1997 the Valuation Lists
issued in November 1997 included the subject property with R.V. fixed
at £22 on buildings and £500 absolute. This was appealed
and in July 1998 the Commissioner issued his decision leaving the assessments
unchanged. The matter was then appealed to the Tribunal.
2. Agreed Rateable Valuations
Negotiations resulted in the rateable valuation for the buildings being
agreed at £18 and for horsepower at £15.
3. Situation
The property is situated in an agricultural area approximately two miles
north-east of Summerhill, Co. Meath and 14 miles from Clonee, Co. Meath
where the company has a processing plant and 23 miles from Dublin city
centre.
4. The Property
The property comprises a sand and gravel pit in operation for approximately
4 years. The sand and gravel is extracted by front loader and is fed
to the processing plant on site where it is washed and screened. The
graded sand and gravel is then sent to the ready-mix and block making
plant in Clonee.
5. Output
The production of sand and gravel from the site has averaged about 245,000
tonnes annually.
6. Ex-Pit price for sand and gravel @ valuation date £3.50
per tonne
Using the sand and gravel wholesale price sale index £2.90 per
tonne
7. Freehold
The Appellant's Case
Mr. Barnett in his evidence stated interalia:
1. The sand and gravel pit has the benefit of full planning
permission from Meath County Council and it is a condition of the planning
condition that workings must keep a minimum of one metre above the water
table.
2. The site adjoins a Meath County Council landfill site and therefore
ground water is polluted and water is taken from an adjoining stream
with an appropriate system installed.
3. The deposit is quite silty and must be washed.
4. Water must be brought in daily for the workmen on site.
5. As a consequence of the above this is an expensive site to operate.
6. As at the valuation date the pit has a remaining life of approximately
18 months.
7. There are no further reserves in the area.
8. Due to the limited life of the pit the cost of the plant and equipment
would have to be amortised over a very short period and therefore the
royalty fee should be reduced by 5% to reflect this disability.
9. The appropriate royalty is 10% of the ex-pit price at 1988 i.e. £0.29
per tonne.
10. There are virtually no direct sales from the pit and all the products
are washed and screened on site and sent directly to Kilsaran's ready-mix
and block work plant at Clonee.
11. In relation to the Tribunal decision in Appeal No: VA96/2/044 -
Dan Morrissy Ltd. which is an appendix to the Respondent's précis
of evidence he stated that he probably had not explained himself properly
in relation to royalty values and that his evidence had been taken out
of context.
12. His valuation was calculated as follows:
245,000 tonnes of sand and gravel @ royalty of £0.29
per tonne = £71,050 p.a.
Rateable valuation @ 0.5% of rental value (N.A.V.) = £355.25
Disability allowance (based on the life of the deposit is insufficient
fully amortised the capital investment in the plant and equipment and
infrastructure on the site) 5%
Rateable valuation therefore £337.50.
This figure does not include the agreed rateable valuations on buildings
of £18 and horsepower £15.
In cross-examination Mr. Barnett conceded that the deposits
are clean and above the water table and that when transported to Clonee
they are upgraded to ready-mix and concrete blocks.
The Respondent's Case
Mr. Colfer in his evidence stated interalia:
1. This is a well-developed sand and gravel pit with clean
deposits and all workings above the water table.
2. That his initial assessment was based on information that the output
was 225,000 tonnes per annum but this was not agreed at 245,000 tonnes
per annum and he was therefore now proposing a rateable valuation of
£540 absolute including £15 agreed for horse-power and with
the addition of £18 agreed for the buildings.
3. That there is no problem with the extraction.
4. That all products is sent to the Clonee processing plant where it
is upgraded to ready-mix and blocks and that Clonee is ready convenient
to Dublin.
5. That the appropriate royalty fee is 15% of the ex-pit price adjusted
to 1988 i.e. of £2.90.
6. That Mr. Barnett in his evidence in the Tribunal case VA96/2/044
- Dan Morrisey Ltd. had submitted:
(a) The formula applied by the Valuation Office in arriving at rateable
valuations appeared right for sand and gravel pits (subject that provided
each case must be examined on its own merits).
(b) Sand and gravel royalties compared favourably with those encountered
in the study of royalties in N.W. England and N. Wales. A £0.50
per tonne sand and gravel royalty would apply as an average here with
royalties being higher nearer Conner Patience?? and lower in the country
areas. Mr. Barnett is aware of a pit near Anfield where a royalty charge
of £0.55 per tonne was being paid.
(c) Mr. Barnett valued quarries and gravel pits by capitalising royalties
in arriving at his opinion of value he usually applies the following
rates or charges;
Stone £0.18 to £0.20 per tonne
Sand & Gravel £0.60 to £0.70 per tonne
Less sand £0.75 per tonne
Both Mr. Barnett's précis of evidence in the Morrissey
case and the Tribunal judgment are appended in full to Mr. Colfer's
précis of evidence.
Mr. Colfer proposed three methods of valuation as follows;
(note that the agreed tonnage of 245,000 has been used in each method
as set out below)
Method 1 - Application of the Valuation Office Formula
First 50,000 tonnes @ £.0028 per tonne R.V. £140
Next 50,000 tonnes @ £.0024 per tonne R.V. £120
Remainder 145 tonnes @ £.00185 per tonne R.V. £268.25
Total R.V. £528.00
Add 308 horse-power @ £0.05 R.V. £ 15 (Agreed)
Total R.V. £543.00
Method 2 - As a % of an ex-fit price
An ex-fit price of £3.50 per tonne adjusted to £2.90 per
tonne as at November 1988 is agreed with the appellants. Because of
the location of the pit and the quality of the extract a 50% royalty
is adopted thus giving a royalty of £0.43 per tonne.
Output: 245,000 tonnes @ £0.43 per tonne = £145,350
R.V. @ 0.5% = £526.75
Add : Horsepower as above £15.00 Total £541
Method 3 - Application of £0.60 tonne minimum royalty
By applying the minimum range of £0.60 usually applied by Mr.
Barnett in arriving at his opinion of value adjusted to £0.50
to November 1988 gives:
245,000 @ £0.50 tonne = £122,500
R.V. @ 0.5% = £612.50
Add : Horse power as before = £15
Total = £627
Mr. Colfer therefore proposed £540 for the appropriate
rateable valuation with an addition £18 for the buildings.
In cross-examination Mr. Colfer stated:
1. That they were not double handling costs and having
the processing plant off the site as it involved only one extra unloading
of vehicles and thus there was no advantage of having upgrading equipment
on the site.
2. In relation to his first method of valuation that the
Morrissey case had not overturned the traditional Valuation Office method
in that the Tribunal stated has stated that the formula method was inappropriate
for stone but did not state that it was inappropriate for sand and gravel.
3. In the hypothetical case that the pit was actually
beside the plant at Clonee he would still apply a royalty of 15%. Ballynamona
was not too disadvantageous but he did accept that it was at some disadvantage.
4. In relation to his third method of valuation he accepted
that in the Morrissey case the Tribunal might have taken Mr. Barnett's
evidence out of context.
5. There was a lack of evidence of royalties for sand
and gravel pits because most sites were owner occupied rather than leased.
Determination
The basic facts in relation to this case were agreed between the parties
and the dispute centres on the appropriate method of valuation and the
percentage royalty of the ex-pit price. The appellant adopts one method
of valuation only namely a royalty, which is a percentage of the ex-pit
price while the respondent provides three methods. The second of which
is the same as the appellants, the others being a Valuation Office formula
basis and the application of a minimum price per tonne royalty.
The Valuation Office formula method was arrived at in
1979 and following the Supreme Court decision in the Roadstone case
in 1955 (this statement is contained on page 4 of the Tribunal judgment
in VA96/2/044 which was an Appendix to the respondent's précis
of evidence). It seems inappropriate to this Tribunal that fixed rates
per tonne should apply irrespective of the location of the pit, the
quality of its deposit or the costs involved in its deduction. We therefore
will not follow this method in this case.
In relation to the third method the application of a minimum
£0.60 per tonne royalty, Mr. Colfer greatly acknowledged in cross-examination
that Mr. Barnett's evidence in a previous case had been mis-interpreted
and he effectively withdrew his method from consideration. In any event
he did appear to rely on the figure that this method produced which
was considerably higher than the figure produced under the other two
methods and his proposal of the correct rateable valuation which was
somewhat less than the average of the figures produced under methods
one and two, both of which were very similar in any event.
We have therefore decided that the valuation method common
to both parties namely a royalty that has a percentage of the ex-pit
price is appropriate in this case. The ex-pit price as at 1988 is agreed
at £2.90 per tonne. Mr. Barnett for the appellant suggested the
appropriate percentage to be 10% i.e. £0.29 per tonne and made
a further reduction called a disability allowance of 5%. Mr. Colfer
for the respondent adopted a royalty of 15% of the ex-pit price, which
is £0.43 per tonne and made no deduction on that figure.
The Tribunal considers that the subject pit is dis-advantaged
on the grounds:
1. Of its distance from the processing plant which incurs
some additional handling expenditure.
2. The relatively short life of the deposit and the effect of that on
the amtisation of capital investment in plant and equipment and infrastructure
on the site.
The Tribunal determines the rateable valuation as follows:
245,000 tonnes of sand & gravel at a royalty of 15%
of the 1988 ex-pit price of £2.90 = £0.435 x £245,000
= £106,575 less 10% for distance from the plant and relatively
short life of the deposit = £10,657.50 subtracting that from the
figure above gives £95,917.50. N.A.V. @ 0.5% = £479.58.
Say £480.00 Add: Horsepower agreed at £15 = £495 and
buildings agreed at £18. Total £513.
And the Tribunal so determines.